Update on 18th Avenue & 12th Avenue Projects

No photo description available.

12th Avenue is projected to fully open by Wednesday with side street work to be continued and sod laid. The contractor has till November 27th to complete the project with our penalty. They may have to laid sod in the spring weather dependent.

18th Avenue is supposed to pour the concrete lane this Wednesday, again weather dependent. Concrete can’t be poured when the temperatures are below 35 degrees. The contractor has till November 22 to complete the work without penalty.